Roadworks Programmed roadworks with the next month include: Commencement of reconstructing and widening the final single lane section of Franks Road, Blackbutt to a two lane sealed standard. Construc
Roadworks
Programmed roadworks with the next month include:
- Commencement of reconstructing and widening the final single lane section of Franks Road, Blackbutt to a two lane sealed standard.
- Constructing a bikeway on the northern side of Alford Street between the Kingaroy Pool and First Avenue.
- Shoulder improvements on the Corndale Road east of Memerambi
- Continuation of Intersection Improvements on the Bunya Highway at Coolabunia.
- Reconstruction of badly deformed sealed section of Kitoba Road, north west of Murgon
- Gravel resheeting of Copper Creek Road, Maidenwell
- Gravel resheeting in the Burrandowan area
- Reconstruction of a deformed sealed section of Mt Stanley Road, East Nanango