Cr Gavin Jones - Roads & Drainage Portfolio Report - 19 April 2017

Back

Roadworks Programmed roadworks with the next month include: Commencement of reconstructing and widening the final single lane section of Franks Road, Blackbutt to a two lane sealed standard. Construc

Roadworks

Programmed roadworks with the next month include:

  • Commencement of reconstructing and widening the final single lane section of Franks Road, Blackbutt to a two lane sealed standard.
  • Constructing a bikeway on the northern side of Alford Street between the Kingaroy Pool and First Avenue.
  • Shoulder improvements on the Corndale Road east of Memerambi
  • Continuation of Intersection Improvements on the Bunya Highway at Coolabunia.
  • Reconstruction of badly deformed sealed section of Kitoba Road, north west of Murgon
  • Gravel resheeting of Copper Creek Road, Maidenwell
  • Gravel resheeting in the Burrandowan area
  • Reconstruction of a deformed sealed section of Mt Stanley Road, East Nanango