Cr Gavin Jones - Roads Portfolio Report - 15 November 2017
Back
Roads & Drainage Construction Crew North - Corndale Road, Memerambi (R2R shoulder widening & overlay from Klass and Townes intersection 0.7 km east) - Works are on schedule with 80% complete
Roads and Drainage
- Construction Crew North - Corndale Road, Memerambi (R2R shoulder widening & overlay from Klass and Townes intersection 0.7 km east) - Works are on schedule with 80% complete; pavement material has been spread and compacted. This will be followed by the bitumen seal and line marking within the next (2) two weeks
- Construction Crew Central – Kumbia Road, Kumbia (widen and overlay between ch. 17950 – 18840, 890m) - Work has recently commenced with the clearing completed and the formation works underway. These works are expected to be completed in February 2018
- Construction Crew South - Grader Maintenance - Blackbutt and Taromeo-Benarkin area
- Concrete Construction Crew - Kingaroy Street (children crossing upgrade Taabinga School) - Work is progressing well with 60% of the work completed. The expected completion date is late November.
- Concrete Construction Crew – Hart Street, Blackbutt (concrete footpath W4Q
- Between the Blackbutt Hotel and the retirement village) - Work is on schedule with 90% of the new concrete footpath complete and in use. Two vehicle accesses are to be completed this week which will finalize the project.
Heavy Maintenance South
Grader maintenance:
- Manumbar Road, Glan Devon - Shoulder Maintenance
- Maidenwell area – W4Q Resheeting
Recently completed:
- McIllhatton Road – Grader Maintenance (TC Debbie flood restoration)
General Maintenance South
- Parker Road, Ellesmere – W4Q Drainage works
- Runnymede Road – Capital Drainage works (culvert extensions)
- General Maintenance works
Heavy Maintenance Central
Grader Maintenance
- Goodger & Alice Creek area – Grader Maintenance
- Goodger area – W4Q Resheeting
Recently completed:
- Kumbia Back Road – W4Q Resheeting
- Haly Creek Road – W4Q Resheeting
General Maintenance Central
- Markwell & Mant Street – W4Q Drainage works
- General Maintenance works
Heavy Maintenance North
Grader maintenance:
- Stonelands area – Grader Maintenance
- Mondure area – W4Q Resheeting
Recently completed:
- Borcherts Hill - Resheeting
- Wesslings Road – W4Q Resheeting
General Maintenance North
- Dutton Street, Murgon – Construct disability parking bay
- General Maintenance works
RMPC
- D’Aguilar Hwy – Pavement repairs (from Meandu Creek to Sommerfelds Lane)
- Silting and Drainage works (adjacent to overtaking lane Coolabunia)
- Kingaroy Street - Pavement repair
- Kilcoy Murgon Road – Pavement repair (at floodway near Goschnicks Road)
Slashing:
- All available slashers including contractors working under the Maintenance Supervisors control.
- TMR roads when available
- Chinchilla Wondai Road & Durong area contractor operating
Programmed Works (approx. start end of month)
- D’Aguilar Hwy – Spot shoulder works (southern boundary to Nanango)
- Kingaroy Cooyar Road – Spot shoulder works (various locations)
- Bunya Hwy (45A) Dalby Road – Spot shoulder works (various locations)
Reseals
- Coolabunia area - Finalising prep works
- Patching works when required
- Sealing program expected to commence 20th November