Cr Gavin Jones - Roads & Drainage Portfolio Report - 13 December 2017
Back
Roads & Drainage Construction Crews – December Works Corndale Road, Memerambi R2R Final bitumen seal is programmed for Friday 8th December Line marking is programmed in the week beginning
Roads and Drainage
- Construction Crews – December Works
- Corndale Road, Memerambi R2R
- Final bitumen seal is programmed for Friday 8th December
- Line marking is programmed in the week beginning 11th December
- J Hunters Rd
- Grade and Re-sheet programmed to commence in the week beginning 11th December
- Kumbia - Road, Kumbia
- Widening and overlay continuing
- Expected to be completed prior to Christmas
- Bell St, Kumbia
- Upgrade Children Crossing & Widening of Bell Street
- Work is expected to be completed over the Christmas School holiday period
- Blackbutt and Taromeo-Benarkin area -Grader Maintenance
- Ulampa Rd
- Googa Creek Rd
- Pamela Drive
- Cairns St, Nanango
- Works commenced on Monday 4th December
- First concrete pour was done Thursday 7th Dec.
- Completed – November Works
- Haly St, Kingaroy - concrete Footpath (MacDonald’s to William St)
- Hart Street, Blackbutt
- Kingaroy Street (children crossing upgrade Taabinga School)
- Memerambi Barkers Ck. Rd - Grade and Re-sheet in the vicinity of the feedlot is completed
- Maintenance Crews – Works Underway
- Grader maintenance
- Manumbar Road, Glan Devon
- McNamara Road, Nanango
- Swenson Road, Hodgleigh
- Recreation Drive, Wooroolin
- Mt Hope Road, Booie
- Boondooma Dam
- General Maintenance works
- W4Q
- Markwell & Mant Street – W4Q Drainage works
- Parker Road, Ellesmere – W4Q Drainage works
- Capital Works
- Runnymede Road – Capital Drainage works ( culvert extensions)
- Rodney Street, Proston – Construct footpath & disability parking bay
- Lamb Street – Pram Ramp
- Completed – November Works
- Scott’s Lane, Runnymede
- Farrers Road – Grader Maintenance
- Goodger & Alice Creek area – Grader Maintenance
- Goodger area – W4Q Resheeting
- Maidenwell Upper Yarraman Rd – Grader Maintenance
- RMPC - Ongoing
- D’Aguilar Hwy – Contracted Works
- Silting & drainage works adjacent to overtaking lane Coolabunia
- Pavement repairs Coolabunia area/ Somerfield Lane
- Maidenwell Bunya Mountains Road formation grade
- Byee Rd – Contracted Works
- Stabilising reseal prep
- Reseals
- Estimated 97% completed, Contractor currently working in Nanango streets and expected to complete all reseal works in rural areas.
- Slashing
- All available slashers including contractors working under the Maintenance Supervisors control.
- TMR roads to follow