Cr Gavin Jones - Roads & Drainage Portfolio Report - 18 April 2018

Back

Roadworks Construction Crews – April Works: Old Rifle Range Road, Nanango – Widen & Overlay Construction Works have been completed – waiting for final bitumen seal Haly St, Kin

Roadworks

Construction Crews – April Works:

Old Rifle Range Road, Nanango – Widen & Overlay

  • Construction Works have been completed – waiting for final bitumen seal

Haly St, Kingaroy – Concrete footpath (Fisher St to Tessmanns Road)

  • Concrete footpath has been completed between Fisher & Tuite St
  • Section between Tuite St  and Murphy St is under construction

Gore St, Murgon – Concrete Footpath - Upgrade the concrete footpath from Stephens St to Dutton St (western side)

  • First section from Stephens St to the School has been competed (Approx. 100m)
  • Works are progressing from the School to Dutton St

Wattlecamp Road, Wattlecamp -Widen & Overlay

  • Clearing to recommence in the week beginning the 16th of April to remove the trees holding the wildlife(Bats)
  • Northern end of the project  has had the Emulsion seal
  • Works are in progress on the next 400m section

Murphys Rd – Crawford - Upgrade existing gravel road to a two-way bitumen sealed road

  • Construction Works have been completed with the first coat seal in place
  • Final Bitumen Seal due this month (waiting on Contractor)

Memerambi Barkers Ck Road – Realignment

  • Approval to commence work has been given (Cultural Heritage)
  • Clearing commenced 10 April.

Completed – April Work:

  • Kumbia Road Completed  - waiting on final bitumen seal
  • Kumbia School Completed – waiting on final bitumen seal
  • Murphy’s Road completed  - waiting on final bitumen seal
  • Old Rifle Range Road Completed – waiting on final bitumen seal

Maintenance Crews - Works Planned for April:

Maintenance Grading:

  • Kinleymore School Road
  • Faughnans Road
  • Half Mile Creek Road (TC Debbie restoration works)

Resheeting

  • Walsh Road
  • Manumbar Road
  • Glencoe Road
  • Coverty Road (W4Q) commencing
  • Zolner Road
  • Liesegangs Road
  • Old Taabinga Road + TC Debbie Restoration works
  • Minmore Road + TC Debbie restoration works
  • Foleys Road + TC Debbie restoration works

Completed – March / April:

Grader maintenance

  • Okeden Byanda Rd
  • Speedwell School Road
  • Foxs Road
  • Luck Road
  • McAuliffes Road
  • Althause Road
  • Holdings Road
  • Niagara Road
  • Franklins Road
  • Wiedens Road
  • Bilboa Road
  • Haydens Road + TC Debbie Restoration works
  • Hoopers Road
  • Hodges Road
  • Radunz Road
  • Snowys Knob Road
  • River Road, Bullcamp

Resheeting

  • Franklins Road
  • Melrose Road
  • Hunters Road
  • Byanda Road
  • Redvale Road
  • Bullcamp Runnymede Road intersection with River Road

Minor Contractor – April:

RMPC - Works programed

  • Kingaroy Burrandowans Rd
  • Shoulder grader maintenance & resheeting
  • Shoulder stabilising & sealing (0.0-1.2 km)
  • Formation grade
  • Formation resheeting (approx. 1 km)
  • Bunya Hwy
  • Stabilising/Pavement repairs

Bitumen Reseals – Works programed

  • Boondooma Dam Camp Area roads
  • Reseal
  • River Rd Kingaroy
  • Prep-works - pavement repairs

RMPC – Works completed

  • Pavement repairs by stabilisation Nanango – Kingaroy Coolabunia area/ Somerfield Lane
  • Memerambi Gordonbrook Rd formation grade started 14th March
  • Clearing & mulching Coolabunia area storm damage commencing 5th March