Cr Gavin Jones - Roads & Drainage Portfolio Report - 18 April 2018
Back
Roadworks Construction Crews – April Works: Old Rifle Range Road, Nanango – Widen & Overlay Construction Works have been completed – waiting for final bitumen seal Haly St, Kin
Roadworks
Construction Crews – April Works:
Old Rifle Range Road, Nanango – Widen & Overlay
- Construction Works have been completed – waiting for final bitumen seal
Haly St, Kingaroy – Concrete footpath (Fisher St to Tessmanns Road)
- Concrete footpath has been completed between Fisher & Tuite St
- Section between Tuite St and Murphy St is under construction
Gore St, Murgon – Concrete Footpath - Upgrade the concrete footpath from Stephens St to Dutton St (western side)
- First section from Stephens St to the School has been competed (Approx. 100m)
- Works are progressing from the School to Dutton St
Wattlecamp Road, Wattlecamp -Widen & Overlay
- Clearing to recommence in the week beginning the 16th of April to remove the trees holding the wildlife(Bats)
- Northern end of the project has had the Emulsion seal
- Works are in progress on the next 400m section
Murphys Rd – Crawford - Upgrade existing gravel road to a two-way bitumen sealed road
- Construction Works have been completed with the first coat seal in place
- Final Bitumen Seal due this month (waiting on Contractor)
Memerambi Barkers Ck Road – Realignment
- Approval to commence work has been given (Cultural Heritage)
- Clearing commenced 10 April.
Completed – April Work:
- Kumbia Road Completed - waiting on final bitumen seal
- Kumbia School Completed – waiting on final bitumen seal
- Murphy’s Road completed - waiting on final bitumen seal
- Old Rifle Range Road Completed – waiting on final bitumen seal
Maintenance Crews - Works Planned for April:
Maintenance Grading:
- Kinleymore School Road
- Faughnans Road
- Half Mile Creek Road (TC Debbie restoration works)
Resheeting
- Walsh Road
- Manumbar Road
- Glencoe Road
- Coverty Road (W4Q) commencing
- Zolner Road
- Liesegangs Road
- Old Taabinga Road + TC Debbie Restoration works
- Minmore Road + TC Debbie restoration works
- Foleys Road + TC Debbie restoration works
Completed – March / April:
Grader maintenance
- Okeden Byanda Rd
- Speedwell School Road
- Foxs Road
- Luck Road
- McAuliffes Road
- Althause Road
- Holdings Road
- Niagara Road
- Franklins Road
- Wiedens Road
- Bilboa Road
- Haydens Road + TC Debbie Restoration works
- Hoopers Road
- Hodges Road
- Radunz Road
- Snowys Knob Road
- River Road, Bullcamp
Resheeting
- Franklins Road
- Melrose Road
- Hunters Road
- Byanda Road
- Redvale Road
- Bullcamp Runnymede Road intersection with River Road
Minor Contractor – April:
RMPC - Works programed
- Kingaroy Burrandowans Rd
- Shoulder grader maintenance & resheeting
- Shoulder stabilising & sealing (0.0-1.2 km)
- Formation grade
- Formation resheeting (approx. 1 km)
- Bunya Hwy
- Stabilising/Pavement repairs
Bitumen Reseals – Works programed
- Boondooma Dam Camp Area roads
- Reseal
- River Rd Kingaroy
- Prep-works - pavement repairs
RMPC – Works completed
- Pavement repairs by stabilisation Nanango – Kingaroy Coolabunia area/ Somerfield Lane
- Memerambi Gordonbrook Rd formation grade started 14th March
- Clearing & mulching Coolabunia area storm damage commencing 5th March