Search our site...

UPDATE - Lamb Street, Murgon - CBD Footpath, Kerb and Channel Replacement

Back

Following the success of Stage Two, South Burnett Regional Council is pleased to be proceeding with Stage Three of the Lamb Street Footpath, Kerb and Channel Replacement works.

New footpath surfacing works will be undertaken to complete frontages adjoining The Australian and The Royal Hotel, located on Gore Street’s western side. Complete replacement of the footpath and kerb and channel will also commence between the BIEDO office on Gore Street extending around to The Rail Trail on Lamb Street.

South Burnett Regional Council has a strong and continued commitment to supporting regionally based suppliers and contractors throughout the delivery of the project.

Details of activities planned for week commencing Monday 19 October 2020 are outlined below and highlighted in the attached “Image – Plan of works”. GREEN Sections are considered complete. 

Week commencing Monday 19 October 2020  

  • BLUE - Stormwater infrastructure replacement commencing Monday 19 October 2020
  • ORANGE - Demolition works completed - Kerb and channel works commencing week of the 19 October 2020   
  • RED - Footpath repairs and Spraypave resurfacing

Motorists and pedestrians are requested to travel with extreme care, to drive to the prevailing road conditions and to adhere to signage. Council apologises for any inconvenience caused and thanks you for your patience whilst works are in progress. 

Should you have any questions or concerns regarding any facets of the project, please contact Council’s Infrastructure team by phone on 4189 9100 or email Council.  

Lamb St Murgon

 

Image: Planned Works for Murgon’s Footpath Replacement Program