Cr Gavin Jones - Roads & Drainage Portfolio Report - 13 June 2018
Back
Roadworks Construction Crews – May/June Works Haly St, Kingaroy – Concrete footpath (Fisher St to Tessmanns Road) Concrete footpath has been completed between Fisher & Willowglen St S
Roadworks
Construction Crews – May/June Works
Haly St, Kingaroy – Concrete footpath (Fisher St to Tessmanns Road)
- Concrete footpath has been completed between Fisher & Willowglen St
- Section between Willowglen St and Tessmanns is under construction
Wattlecamp Road, Wattlecamp -Widen & Overlay
- The first 700m of the project has been completed
- Works are in progress on the remaining 500m section
Memerambi Barkers Ck Road – Realignment
- Clearing and grubbing completed
- Earthworks in progress
Manar Road – Floodway repairs/ TC Debbie Betterment
- Scour protection work has commenced
Completed – May Work
- Gore St, Murgon concrete footpath completed
Maintenance Crews - Works Planned for June
Maintenance Grading :
- Minor grader maintenance as crews are currently focused on TC Debbie and gravel resheeting works
- Meehans Road
- Cooleys Road
- Spencers Road
Resheeting
- Glencoe Road
- Coverty Road
- TH Burns Road
- Childs Road
- Haydens Road
- Broadmans Road
- Brooklands Pimpimbudgee Road (shoulder resheeting)
- Muller St
- Ridley St
Completed – May Work
Grader maintenance/TC Debbie repairs
- Kunioon Road
- Goodger Gully Road
- Welch Road
- Foleys Road
- West Wooroolin Road
- White Rock Road
Resheeting
- Walsh Road
- Kawl Kawl Road
- Zolner Road
- Minmore Road
- Manumbar Road
Contract Work – May/June
Rogers Drive roundabout - Kingaroy
- Work has commenced with clearing and grubbing completed, and earthworks underway.
RMPC - Works completed
Kingaroy Burrandowan Rd
- Formation resheeting completed