Works Update - Murgon CBD

Back

South Burnett Regional Council advises the continuation of works and additional upcoming works at Lamb Street, Murgon CBD.

Planned works include:

  • Spraycrete footpath works at The Royal Hotel, The Australian Hotel and Commonwealth Bank and various touch ups through CBD footpath – scheduled from Thursday 4 March to Thursday 18 March 2021
  • Concrete slab and stone monument near Gore Street – scheduled from Monday 8 March to Friday 19 March 2021
  • Anzac Memorial decorative concrete and furniture installation – scheduled from Monday 15 March to Friday 26 March 2021
  • Kerb ramp Tactile Ground Surface Indicator installation – scheduled from late March 2021
  • Kerb painting and paint touch ups through CBD – scheduled from early April 2021
  • Brass discs remaining installation – scheduled from early April 2021
  • CBD Footpath Cleaning – scheduled from mid-April 2021 (night works)

The works scheduled are subject to weather and other external constraints.

The installation works have been funded under Council’s 2020/21 Capital Works program.

To provide a safe work environment, the work areas will be controlled by signage or with traffic controllers as required.  Council apologises for any inconvenience caused and appreciates your patience whilst works are in progress.

For further information contact Council’s Infrastructure team on 4189 9100 or email info@sbrc.qld.gov.au