UPDATE - Lamb Street, Murgon - CBD Footpath, Kerb and Channel Replacement – 14-06-20

Back

South Burnett Regional Council is pleased to advise the progress of the replacement of Murgon’s CBD footpath along Lamb Street (between Krebs and Gore Street’s).

funded through the Queensland Government’s 2019-21 Works for Queensland program (W4Q R3) and South Burnett Regional Council. Detailed planning has preceded works in order to ensure all businesses can remain operational during the construction period.
Continuation of the street’s southern footpath replacement construction works are scheduled to be delivered during night works, operating between 6pm and 6am. Additional supporting tasks being conducted during standard working hours as required.
Details of activities planned for the week commencing Sunday 14 June are outlined below and highlighted in the “Image – Plan of works”. GREEN Sections are considered complete.

Week commencing Sunday 14 June 2020

RED Southern Section 1 - Intersection of Krebs Street and Lamb Street to centre of NAB building – remaining section

  • Partially complete
  • Remaining works to be completed between critical sections

YELLOW Southern Section 3 - NAB ATM to South Burnett Lawyers – remaining section

  • Partially completed.
  • Concreting adjacent to Florist Tuesday 16 June
  • Concreting adjacent to Lawyers Wednesday 17 June

ORANGE Southern Section 4a - Coffee Bar lowermost access to Murgon News

  • Demolition of remaining disability bay Sunday 14 June
  • Concreting to follow completion of section 3

BLUE Southern Section 5 - Murgon News to South Burnett Lawyers.

  • Kerb and channel pour Thursday 18 June

GREY Northern spraypave concrete application in highlighted section

Motorists and pedestrians are requested to travel with extreme care, to drive to the prevailing road conditions and to adhere to signage. Council apologises for any inconvenience caused and thanks you for your patience whilst works are in progress.

Should you have any questions or concerns regarding any facets of the project, please contact Council’s Infrastructure team by phone on 4189 9100 or email.