UPDATE - Lamb Street, Murgon - CBD Footpath, Kerb and Channel Replacement – 24-05-20

Back

Council is pleased to provide an update on the progress of the replacement of Murgon’s CBD footpath along Lamb Street (between Krebs and Gore Streets).

Funded through the Queensland Government’s 2019-21 Works for Queensland program (W4Q R3) and South Burnett Regional Council. Northern construction works have reached practical completion, with continuation of the southern footpath replacement works ongoing. Detailed planning has preceded works in order to ensure all businesses can remain operational during the construction period.

The street’s southern construction works are scheduled to be delivered during night works, operating between 6pm and 6am. Additional supporting tasks are being conducted during standard working hours.

The past week has seen Council’s contractors efficiently rectify pre-existing subsoil issues, with additional rain hindering the week’s overall progress.

Details of activities planned for the week commencing Sunday 24 May are outlined below:

Week commencing Sunday 24 May 2020

Southern Section 1 - Intersection of Krebs Street and Lamb Street to centre of NAB building - Highlighted in RED in the image below. To be completed between kerb pours.

Southern Section 2a - Intersection of Gore Street and Lamb Street - highlighted in BLUE in the image below. Concrete pour progressed Friday 22 May 2020.

Southern Section 3 - NAB ATM to South Burnett Lawyers - highlighted in YELLOW in the image below. Kerb and channel to progress Monday 25 May 2020. Concrete preparation to commence following kerb and channel pour.

Southern Section 4 - Furniture Zone to Café’s lowermost access - highlighted in PURPLE in the image below. Kerb and channel to progress Monday 25 May 2020. Concrete to commence following section 3 completion.

Southern Section 4a - Café’s lowermost access to Murgon News- highlighted in ORANGE in the image below. Demolition scheduled for Sunday 31 May 2020.

Northern spray pave concrete application - Colour application scheduled between 5 May and 6 June 2020.

Motorists and pedestrians are requested to travel with extreme care, to drive to the prevailing road conditions and to adhere to signage. Council apologises for any inconvenience caused and thanks you for your patience whilst works are in progress.

Should you have any questions or concerns regarding any facets of the project, please contact Council’s Infrastructure team by phone on 4189 9100 or email.

plan of works

Image - Plan of works

The Murgon CBD Footpath project has been funded by the
Queensland Government’s Works for Queensland program and South Burnett Regional Council.

 

 

work in progress